Almost any construction project — new buildings, additions, decks, electrical work, plumbing, mechanical systems — requires a building permit from Clare County. The process starts at the township level, then moves to the county.
Do I Need a Permit?
You likely need a permit if you are:
- Building anything new (house, garage, pole barn, shed over 200 sq ft)
- Adding on to an existing structure
- Doing electrical, plumbing, or mechanical work
- Installing or replacing a roof (in some cases)
- Putting in a deck or porch
You probably do not need one for minor repairs, painting, or small sheds under 200 square feet. When in doubt, call the county at (989) 539-2761.
Steps to Get Your Permit
- Get a township zoning permit first. Contact Dick Hassberger at (989) 588-9841 ext. 5. Submit a Zoning Permit Application with a site plan. The township confirms your project meets local zoning rules.
- Apply for the county building permit. Bring your approved zoning permit plus construction plans to the Clare County Building Department. Plans should include dimensions, materials, structural details, and a site drawing.
- Pay the permit fee. Fees are based on project value and type. Expect $75-$300 for typical residential projects.
- Post your permit. Display it at the job site where inspectors can see it.
- Call for inspections. The county requires inspections at specific stages — footing, framing, insulation, and final are common. Schedule each one before moving to the next phase.
- Get final approval. Once the final inspection passes, you receive a certificate of completion.
Key Details
- Timeline: Permit review typically takes 1-2 weeks.
- Permits expire if work does not start within 6 months.
- Contractors should pull their own permits for trade work (electrical, plumbing).
Common Mistakes
- Skipping the township step. The county requires zoning approval before they will process your building permit.
- Starting work before the permit is issued. This can result in double fees, stop-work orders, or required demolition.
- Not scheduling inspections. Covering up work before an inspection means you may have to tear it out so the inspector can see it.