Getting a Building Permit

How to get a building permit in Clare County, Michigan. When you need one, where to apply, and what inspections are required.
property · county
Last verified: 2026-03-25

Almost any construction project — new buildings, additions, decks, electrical work, plumbing, mechanical systems — requires a building permit from Clare County. The process starts at the township level, then moves to the county.

Do I Need a Permit?

You likely need a permit if you are:

  • Building anything new (house, garage, pole barn, shed over 200 sq ft)
  • Adding on to an existing structure
  • Doing electrical, plumbing, or mechanical work
  • Installing or replacing a roof (in some cases)
  • Putting in a deck or porch

You probably do not need one for minor repairs, painting, or small sheds under 200 square feet. When in doubt, call the county at (989) 539-2761.

Steps to Get Your Permit

  1. Get a township zoning permit first. Contact Dick Hassberger at (989) 588-9841 ext. 5. Submit a Zoning Permit Application with a site plan. The township confirms your project meets local zoning rules.
  2. Apply for the county building permit. Bring your approved zoning permit plus construction plans to the Clare County Building Department. Plans should include dimensions, materials, structural details, and a site drawing.
  3. Pay the permit fee. Fees are based on project value and type. Expect $75-$300 for typical residential projects.
  4. Post your permit. Display it at the job site where inspectors can see it.
  5. Call for inspections. The county requires inspections at specific stages — footing, framing, insulation, and final are common. Schedule each one before moving to the next phase.
  6. Get final approval. Once the final inspection passes, you receive a certificate of completion.

Key Details

  • Timeline: Permit review typically takes 1-2 weeks.
  • Permits expire if work does not start within 6 months.
  • Contractors should pull their own permits for trade work (electrical, plumbing).

Common Mistakes

  • Skipping the township step. The county requires zoning approval before they will process your building permit.
  • Starting work before the permit is issued. This can result in double fees, stop-work orders, or required demolition.
  • Not scheduling inspections. Covering up work before an inspection means you may have to tear it out so the inspector can see it.
Contacts
Clare County Building Department